Road work for the week beginning 6/10/2019

The following road work will take place (weather permitting) during the week of June 10th to June 14th:

Monday June 10th
Township employees will be milling in the Becker development and then move to Laurie Lane between Newport Road and the southern intersection of Brookview Drive.  Cleaning along the curbs will also take place at this time.

Tuesday June 11th
AMS will begin applying material on Oakwood Lane, Buckwood Lane, Spring View Drive, and portions of Woodland Avenue.  Township employees will finish milling and cleaning on Laurie Lane.

Wednesday June 12th
AMS will apply material on Woodland Avenue, Crest Drive, Becker Drive and West Third Avenue.

Thursday June 13th
AMS will apply material on Becker Drive, Shelley Court, and Laurie Lane from Newport Road to the Southern intersection of Brookview Drive.

 

During these times flaggers will be in place and all traffic, emergency vehicles and deliveries should have access.