Road work (revised schedule as of 8/31/2021)

Please see the following adjusted paving schedule (revised as of 8/31/2021):
(This schedule may change again depending on the weather, and residents living along the affected roadways may need to receive an updated notice for the work)
During paving, Township employees will be on site to help with traffic at all times.

Day #1 - Friday August 27th
Application of paving fabric on Anita Drive, Sylvia Drive, Windy Hill Drive, and East Windy Hill Drive. Once the fabric is applied, it is able to be driven on, but residents should still use caution when turning. These streets will also receive a leveling course of pavement on top of the fabric that again can be driven on after it has been rolled.

Day #2 – Monday August 30th
The final wearing course will be applied to Anita Drive, Sylvia Drive, Windy Hill Drive and East Windy Hill Drive. A leveling course and the final wearing course will also be applied to Rabbit Hill Road from SR 772 to Church Road.

Day #3 – Thursday, September 2nd
Milling and paving will take place on Owl Hill Road from SR 501 to the paving joint about 100 feet East of Shober Lane. Local businesses will have access during the paving and Township employees will be on site at all times to help with traffic.

The following detours will be in place:

  • Landis Valley Road to East Woods Drive to Kissel Hill Road to Millport Road to SR 501
  • Cedar Street to East 6th Street to SR 501